Bonny Island Liquified Natural Gas Plant Development by Limult

The Plant

​ The plant ranks amongst the biggest and top performers worldwide; its performance is regularly benchmarked internationally with other LNG plants around the world.

The plant has rapidly and successfully made the transition
from a construction project to a stable production operation, with a robust
framework of people, processes, systems and organisation, as well as relentless
focus on operational excellence and continuous improvement. In addition to
regular maintenance of the assets to assure integrity and reliability,
opportunities are continuously sought to debottleneck the plant, incorporating
proven techniques and processes to maximize production and manage human
interferences and impacts. The plant has also embarked on a structured
programme of asset rejuvenation to extend the plant life beyond the current
design life. All these activities are underpinned by a Health, Safety, Security
and Environment (HSSE) culture that continually seeks improvements in the safe
and sustainable utilisation of our assets.

For NLNG, November 1995 will remain a remarkable month in
its corporate history. That was when the Final Investment Decision (FID) was
taken by the shareholders to build a Liquefied Natural Gas (LNG) plant in
Finima, Bonny Island in Rivers State. This was followed in December 1995 by the
award of a turnkey Engineering, Procurement and Construction (EPC) contract to
a consortium of engineering firms, TSKJ, comprised of Technip, Snamprogetti,
M.W. Kellog and Japan Gas Corporation for the Plant (consisting of two
trains—Trains 1 and 2, called the Base Project), the Gas Transmission System
(GTS) and the Residential Area (RA).

Construction at the Plant site commenced in February 1996
and on August 12, 1999, Train 2 was ready for startup. Production of LNG
commenced on September 15. Train 1 subsequently came on stream on February 27,
2000. The second phase of development, called Expansion Project, commenced with
an FID in February 1999 to develop Train 3 and the Plant's Natural Gas Liquids
(NGLs) Handling Unit (LHU)—condensate stabilisation and Liquefied Petroleum Gas
(LPG) production units. The expansion project was completed and came into
operation in November 2002.

The next phase of development called the NLNGPlus Project,
comprised of Trains 4 and 5, commenced with an FID in March 2002. Train 4 came
on stream in November 2005 and Train 5 was started up I February 2006. NLNGSix
Project, consisting of Train 6 and additional condensate processing, LPG
storage and jetty facilities, commenced with an FID in 2004. Train 6 became
operational in December 2007.

With six trains currently operational, the entire complex is
capable of producing 22 million tonnes per annum (mtpa) of LNG, and 5mtpa of
NGLs from 3.5 Billion (standard) cubic feet per day (Bcf/d) of natural gas
intake.

Plans for building Train 7 which will lift the total
production capacity to 30mtpa of LNG are currently progressing. FID for the
8mtpa train was taken in December 2019, paving the way for the award of
Engineering, Procurement and Construction Contracts to SCD JV Consortium in May
2020. Find out more about Train 7 Project.

​The main elements of the facilities already in operation
are:

Diversified gas supply (Associated Gas and Non-Associated
Gas) and six main dedicated gas transmission pipelines, with four of them
located on-shore.

Six LNG processing units (trains) with a total nameplate
processing capacity of 22mtpa.

Four LNG storage tanks, each with a capacity of 84,200 cubic
metres.

Four LPG refrigerated storage tanks, each with a capacity of
65,000 cubic metres (two each for propane and butane).

Contact Us at +2347052446249 for more information on our refining industry development services or visit our store at www.limult.com/shop to see more products that we make available for the people.